Hi,
I have a job where I need to specify two rectangular ROIs. Then I need to apply each of the two ROIs, one at a time to the first slice in a stack and make some measurements in each ROI. Then I need to select the next slice in the stack and apply the same two ROIs, one at a time to the current stack slice and repeat the same measurements in each ROI. I need to repeat this process for all the slices in the stack. I thought that this would be a job for the ROI manager. But, the ROIs in the ROI Manager are locked to the first slice in the stack.
Suggestions?
Thanks, Phil